We have embarked on a several-year refresh project for the Charles River campus Wi-Fi. The purpose of this project is to:

  • Provide greater capacity and support for the community and new devices that become available
  • Bring current wireless technologies and capabilities to campus
  • Ensure that the wireless network hardware remains supported by its vendor

Roll-out of the new wireless access points will occur on a building-by-building basis. The prioritized listing of facilities and their status can be found below.
This schedule is subject to change based on equipment availability, reprioritization, and scheduling conflicts.

2025-202610 Buick StreetResidence HallResidenceIn Progress

Year Address Building Name Type Status
2025-2026 100 Ashford Street BU Track and Tennis Center Academic / Admin Completed
2025-2026 120 Ashford Street Facilities Management and Planning Academic / Admin Completed
2025-2026 285 Babcock Street Case Physical Education Center Academic / Admin Completed
2025-2026 300 Babcock Street Athletics Academic / Admin Completed
2025-2026 53 Bay State Road Health Policy Institute, OTD Academic / Admin Completed
2025-2026 143 Bay State Road CAS/SMG/UROP Academic / Admin Completed
2025-2026 145 Bay State Road Religion Academic / Admin Completed
2025-2026 147 Bay State Road Wiesel Center for Judaic Studies Academic / Admin Completed
2025-2026 152 Bay State Road International Relations Academic / Admin Completed
2025-2026 185 Bay State Road Danielsen Institute Academic / Admin Completed
2025-2026 211 Bay State Road Catholic Center Academic / Admin Completed
2025-2026 213 Bay State Road Hillel House Academic / Admin Completed
2025-2026 225 Bay State Road The Castle/ BU Pub Academic / Admin Completed
2025-2026 226 Bay State Road History Academic / Admin Completed
2025-2026 232 Bay State Road Political Science Academic / Admin Completed
2025-2026 233 Bay State Road Admissions Academic / Admin Completed
2025-2026 236 Bay State Road Anthropology/Philosophy/Political Science Academic / Admin Completed
2025-2026 2 Cummington Street Biological Science Center Academic / Admin Completed
2025-2026 24 Cummington Street Life ScienceĀ  Engineering Building Academic / Admin Completed
2025-2026 48 Cummington Street College of Engineering Academic / Admin Completed
2025-2026 110-112 Cummington St. Mechanical Engineering Academic / Admin Completed
h o l d d
2025-2026 10 Buick Street Residence Hall Residence In Progress
2025-2026 33 Harry Agannis Way Residence Hall Residence Completed