News
Center for Computing & Data Sciences – Construction Update – 1/28/22
During the weekend of January 29th Due to the winter storm forecasted for Saturday, the only activities on site this weekend will be storm cleanup. During the week of January 31st Installation of curtain wall panels at the tower will continue on the 8th and 9th floors. Delivery and assembly of... More
Center for Computing & Data Sciences – Construction Update – 1/21/22
During the weekend of January 22nd On Saturday, crews will continue buildout of elevators 4, 5, and 6 in the tower's core with the focus being framing the front walls. Installation of mechanical, plumbing and fire protection rough will continue. Crews will be on site assembling and installing curtain wall... More
Center for Computing & Data Sciences – Construction Update – 1/14/22
During the weekend of January 15th On Saturday, crews will continue buildout of elevators 4, 5, and 6 in the tower core with the focus being on framing the front walls. Installation of mechanical, plumbing, and fire protection rough will continue. Crews will be on site assembling and installing curtain... More
Center for Computing & Data Sciences – Construction Update – 1/7/22
During the weekend of January 8th On Saturday, crews will continue buildout of elevators 4, 5, and 6 in the tower’s core with the focus being framing the front walls. Installation of mechanical, plumbing, and fire protection rough will continue. Crews will be on site assembling and installing curtain wall... More
Center for Computing & Data Sciences – Construction Update – 12/17/21
During the weekend of December 18th On Saturday, crews will continue installation of rails and platforms for elevators 4, 5, and 6 in the tower’s core. Activities for intumescent and spray fireproofing of the columns and beams on the upper floors of the tower, and installation of mechanical, plumbing, and... More
Preparing Buildings for Intersession
As we end the semester, Campus Planning & Operations would like to remind you how to conserve energy and keep your workplace safe over the Intersession break. Please follow the guidelines below before leaving your workspace. In offices, turn off all electrical devices (computers, monitors, lights, portable heaters, copiers, printers, coffee... More
Center for Computing & Data Sciences – Construction Update – 12/10/21
During the weekend of December 11th On Saturday, crews will continue installation of rails and platforms for elevators 4, 5, and 6 in the tower’s core. Activities for intumescent and spray fireproofing of the columns and beams on the upper floors of the tower and installation of mechanical, plumbing, and... More
Center for Computing & Data Sciences – Construction Update – 12/3/21
During the weekend of December 4th On Saturday, crews will continue installation of rails and platforms for elevators 4, 5, and 6 in the tower’s core. Activities for intumescent and spray fireproofing of the columns and beams on the upper floors of the tower, and installation of mechanical, plumbing, and... More
Center for Computing & Data Sciences – Construction Update – 11/23/21
During the weekend of November 27th On Saturday, removal of the temporary shoring columns and beams supporting the building’s cantilevers will continue. Crews will also continue installation of rails and platforms for elevators 4, 5, and 6 in the tower’s core. Intumescent fireproofing of the columns in the podium and... More
Center for Computing & Data Sciences – Construction Update – 11/19/21
During the weekend of November 20th On Saturday, removal of the temporary shoring columns and beams supporting the building cantilevers will continue. Crews will also continue installation of rails and platforms for elevators 4, 5, and 6 in the tower’s core. Intumescent fireproofing of the columns in the podium and... More