Boston University proudly announces its attainment of the prestigious GreenSeal GS42 Certification, a testament to its unwavering commitment to environmental stewardship and sustainability. This milestone positions Boston University as a leader in sustainable practices within the higher education sector.
Building Systems and High Heat
Subject: Building Systems and High Heat To: Boston University Faculty, Students, & Staff From: Campus Planning & Operations Date: September […]
Boston University Medical Campus Power Shutdown – October 7-9, 2023
During this period, the following buildings – L, R, A, B, K, E, C, & D – will be powered solely on life safety emergency/generator power.
West Campus Dining Expansion – Construction Update – 6/30/23
General Project Updates This past week saw the following construction activity – metal stud framing, sheetrock installation, rough plumbing installation, […]
Kilachand Hall Phase 2 – Construction Update – 6/16/23
General: Daily Work Hours from 6 am-4 pm. (6 am for interior work per ISD permit) The Traffic Management Plan […]
West Campus Dining Expansion – Construction Update – 3/10/23
During the week of March 13th Minor metal stud framing and electrical work will continue this week, and mechanical rough-in will […]
Kilachand Hall Phase 2 – Construction Update – 3/10/23
Weekend Work – Saturday, March 11th Mass Acoustics: Carpenters focusing on raised floor framing and finishing up gable end header […]
West Campus Dining Expansion – Construction Update – 2/24/23
General Project Information Abatement was completed on 2/24/23, and the contractor has removed the containment area. During the week of […]
West Campus Dining Expansion – Construction Update – 01/27/23
During the week of January 30 Monday, 1/30 – Install temporary fencing at the west end of Claflin Hall (grassy […]