Center for Computing & Data Sciences – Construction Update – 7/29/22
During the weekend of July 30th On Saturday, crews will be working from the elevated platforms continuing the installation of panels at the 5th and 17th-floor soffits. Also on Saturday, in the interior of the building, installation of the atrium’s monumental stair and tower’s communicating stair will continue. Removal of... More
Center for Computing & Data Sciences – Construction Update – 07/22/22
During the weekend of July 23rd On Saturday, crews will be working from the elevated platforms to continue the installation of panels at the 5th and 17th-floor soffits. Also on Saturday, installation of the atrium’s monumental stair and tower’s communicating stair will continue in the interior of the building. Framing, More
Kilachand Hall Phase 2 – Construction Update – 07/22/22
Saturday, July 23rd Work hours for interior work will change to a 6 am - 3:30 pm shift. All exterior work will keep a 7 am start time. BrandSafway to continue with scaffold erection on the Back Street north elevation and construction of the man and material hoist. Royal Steam... More
Kilachand Hall Phase 2 – Construction Update – 07/15/22
Saturday, July 16th Work hours for interior work will change to a 6 am - 3:30 pm shift. All exterior work will keep a 7 am start time. BrandSafway to continue with scaffold erection along the north elevation on Back Street and erection of man and material hoist. Royal Steam... More
Center for Computing & Data Sciences – Construction Update – 07/15/22
During the weekend of July 16th On Saturday, crews will continue working from the elevated platforms on the 5th and 17th-floor soffits. Installation of the formwork for the retaining wall at the rear of the Bay State Road brownstones continues. Also on Saturday, installation of the atrium’s monumental stair and... More
Kilachand Hall Phase 2 – Construction Update – 07/08/22
Saturday, July 9th Work hours for interior work will change to a 6 am - 3:30 pm shift. All exterior work will keep a 7 am start time. BrandSafway to continue with scaffold erection along the north elevation on Back Street and erection of man and material hoist. SOS Demolition... More
Center for Computing & Data Sciences – Construction Update – 07/08/22
During the weekend of July 9th On Saturday, crews will continue working from the elevated platforms finishing the 15th and continuing with 17th-floor soffits. Installation of the formwork for the retaining wall at the rear of the Bay State Road brownstones will also continue. Also on Saturday, installation of the... More
Center for Computing & Data Sciences – Construction Update – 07/01/22
During the weekend of July 2nd On Saturday, crews will continue working from the elevated platforms to construct the 15th and 17th-floor soffits. Installation of the retaining wall at the rear of the Bay State Road brownstones will continue. Also on Saturday, installation of the atrium’s monumental stair and tower’s... More
Kilachand Hall Phase 2 – Construction Update – 07/01/22
Saturday, July 2nd Work hours are 7 am - 3:30 pm. BrandSafway will continue with scaffold erection along the west elevation in the alleyway heading north. SOS demolition will have crew members on site continuing with the saw cutting of slab penetrations for the new exhaust risers and select partition... More
Kilachand Hall Phase 2 – Construction Update – 06/24/22
Saturday, June 25th Work hours are 7 am - 3:30 pm. Now that the fire escape has been removed, BrandSafway will have 12-15 crew members on site erecting scaffolding along the west elevation in the alleyway heading north. SOS Corp will have crew members on site continuing with the saw... More