Kilachand Hall Phase 2 – Construction Update – 10/7/22
General Project Information Daily Work Hours from 7 am - 3:30 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road). ... More
Kilachand Hall Phase 2 – Construction Update – 9/30/22
General Project Information Daily Work Hours from 7 am - 3:30 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road). ... More
Center for Computing & Data Sciences – Construction Update – 9/30/22
During the weekend of October 1st On Saturday, installation of the finishes around the atrium’s monumental stair and tower’s communicating stair will continue. Installation of the carpet and ceiling will continue in the tower. Painting of the stairs and walls will continue throughout. Roofing and green terrace materials will continue... More
Center for Computing & Data Sciences – Construction Update – 9/23/22
During the weekend of September 24th On Saturday, on the exterior of the building, crews will be working from the elevated platforms continuing the installation of panels at the 7th floor soffits. Also on Saturday, on the interior of the building, installation of the atrium’s monumental stair and tower’s communicating... More
Kilachand Hall Phase 2 – Construction Update – 9/23/22
General Project Information Daily Work Hours from 7 am-3:30 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
Center for Computing & Data Sciences – Construction Update – 9/16/22
During the weekend of September 17th On Saturday, crews will be working from the elevated platforms continuing the installation of panels at the 7th-floor soffits on the exterior of the building. Also on Saturday, on the interior of the building, installation of the atrium’s monumental stair and tower’s communicating stair... More
Kilachand Hall Phase 2 – Construction Update – 9/16/22
General Project Information Daily Work Hours from 7 am-3:30 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
Kilachand Hall Phase 2 – Construction Update – 9/9/22
General Project Information Daily Work Hours from 7am-3:30pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey barrier site containment... More
Center for Computing & Data Sciences – Construction Update – 9/9/22
During the weekend of September 10th On Saturday, crews will be working from the elevated platforms, continuing to install panels at the 5th and 7th-floor soffits on the exterior of the building. Also on Saturday, on the interior of the building, installation of the atrium’s monumental stair and tower’s communicating... More
Kilachand Hall Phase 2 – Construction Update – 9/2/22
General Project Information Daily Work Hours are from 7 am - 3:30 pm. The approved BTD Traffic Management Plan for the project remains in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey barrier site containment in place, pedestrian... More