West Campus Dining Expansion – Construction Update – 2/24/23
General Project Information Abatement was completed on 2/24/23, and the contractor has removed the containment area. During the week of February 27th Selective demolition will continue, however no loud work will take place prior to 8 am. Metal studs will be delivered to the site on Monday so that framing can begin... More
Kilachand Hall Phase 2 – Construction Update – 02/24/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 02/17/23
General Project Updates Work continues on the renovations to the Residence Life offices. Interior demolition continued during the week of the 13th. During the weekend of February 18th The contractor will be working Saturday, February 18th to continue demolition. During the week of February 20th There will be no work on Monday, February... More
Kilachand Hall Phase 2 – Construction Update – 2/17/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
Kilachand Hall Phase 2 – Construction Update – 02/10/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 2/10/23
General Project Updates Work continues in the Claflin Hall Residence Life offices, including make safe of the electrical, plumbing, and mechanical systems. Last weekend, a temporary wall was constructed to separate the work zone from the public lobby. The construction crew also installed site fencing in the West Campus Plaza, More
Kilachand Hall Phase 2 – Construction Update – 02/03/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More
West Campus Dining Expansion – Construction Update – 01/27/23
During the week of January 30 Monday, 1/30 – Install temporary fencing at the west end of Claflin Hall (grassy area) in the plaza. Tuesday, 1/31 – Thursday, 2/2 – Clear remaining items left within the old Residence Life office spaces. Thursday, 2/2 & Friday, 2/3 – Start demo of... More
West Campus Dining Expansion Comments/Questions
Kilachand Hall Phase 2 – Construction Update – 1/27/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey... More