Abatement was completed on 2/24/23, and the contractor has removed the containment area.

During the week of February 27th

  • Selective demolition will continue, however no loud work will take place prior to 8 am.
  • Metal studs will be delivered to the site on Monday so that framing can begin on Tuesday. A spotter will be working during the delivery to ensure public safety.