Kilachand Hall Phase 2 – Construction Update – 12/9/22
General Project Information Daily Work Hours from 8 am-4 pm. (Quiet study and exam period) The Traffic Management Plan for […]
Center for Computing & Data Sciences – Construction Update – 12/9/22
During the weekend of December 10th On Saturday, on the interior of the building, crews will continue the installation of […]
Center for Computing & Data Sciences – Construction Update – 12/2/22
During the weekend of December 3rd On Saturday, crews will continue the installation of the finishes around the atrium’s monumental […]
Kilachand Hall Phase 2 – Construction Update – 12/2/22
General Project Information Daily Work Hours from 7 am – 3:30 pm. The Traffic Management Plan for the project has […]
Center for Computing & Data Sciences – Construction Update – 11/23/22
During the weekend of November 26th On Saturday, crews will continue the installation of the finishes around the atrium’s monumental […]
Kilachand Hall Phase 2 – Construction Update – 11/23/22
General Project Information Daily Work Hours from 7 am – 3:30 pm. The Traffic Management Plan for the project has […]
Kilachand Hall Phase 2 – Construction Update – 11/18/22
General Project Information Daily Work Hours from 7 am – 3:30 pm. The Traffic Management Plan for the project has […]
Center for Computing & Data Sciences – Construction Update – 11/11/22
During the weekend of November 12th On Saturday, crews will continue the installation of the finishes around the atrium’s monumental […]
Kilachand Hall Phase 2 – Construction Update – 11/11/22
General Project Information Daily Work Hours from 7 am – 3:30 pm. The Traffic Management Plan for the project has […]
Kilachand Hall Phase 2 – Construction Update – 10/28/22
General Project Information Daily Work Hours from 7 am – 3:30 pm. The Traffic Management Plan for the project has […]