To update the project health, start by navigating to the project
Scroll down and click on the status report tab. You will see a list of all previous project health status updates and the status date for each
Click the New button
On the next page, select the date that the health status is being recorded
On the Overall Status tab you can select the overall project health (Red, Yellow, Green)
You can also designate an individual health status for Schedule, Cost, Resources, and Scope along with comments
Once filled out, press the Submit button