Howard Thurman Center – Construction Update – 12/20/19
Weeks of December 23 and December 30 General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. Secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the... More
Goldman School of Dental Medicine – Construction Update – 12/20/19
During the weekend of December 21: On Saturday and Sunday, work will continue throughout the interior of the seven-story west addition, with the focus on installing flooring, mechanical and electrical devices into the ceiling gird, and completing casework (cabinets and counters) on several floors. On Saturday only, work will continue... More
Geothermal Well Drilling Initiative – Construction Update – 12/20/19
During the week of December 23rd: Parking Lot N The drilling subcontractor will be installing the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N. The testing group will be onsite to perform advanced borehole testing of GT-2. This work involves using acoustic... More
CFA Renovations – Construction Update – 12/20/19
During December 20th – January 3rd: (Please note that there is work scheduled for Saturday, December 21st and Sunday, December 22nd. Also, please note that there is a scheduled shutdown of the building’s heating system on Saturday, December 21st between 6:00 am and 2:00 pm to allow for work to be... More
Goldman School of Dental Medicine – Construction Update – 12/13/19
During the weekend of December 14: On Saturday and Sunday, work will continue throughout the interior of the seven-story west addition, with the focus on installing flooring, mechanical and electrical devices into the ceiling gird, and casework (cabinets and counters). On Saturday only, work will continue on the façade of... More
Geothermal Well Drilling Initiative – Construction Update – 12/13/19
During the week of December 16th: Parking Lot N The drilling subcontractor will be drilling at GT-30 and will be following with the installation of the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N. Soil material stockpiling and handling in the basin... More
CFA Renovations – Construction Update – 12/13/19
During December 13th - December 20th: (Please note that there is work scheduled for Saturday, December 14th and Sunday, December 15th) General: On Monday, December 16th the lower parking lot (Lot D) at 25 Buick St. will be closed as a crane will be utilizing the lot to bring materials onto the lower... More
Howard Thurman Center – Construction Update – 12/13/19
Week of December 16, 2019 General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking... More
Geothermal Well Drilling Initiative – Construction Update – 12/06/19
During the week of December 9th: Parking Lot N The drilling subcontractor will be drilling at GT-29 and will be following with the installation of the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N. Soil material stockpiling and handling in the basin... More
Goldman School of Dental Medicine – Construction Update – 12/06/19
During the weekend of December 7: On Saturday and Sunday, work will continue throughout the interior of the seven-story west addition, with the focus on installing terrazzo flooring on the first floor, touch-up painting, along with the continued installation of fixtures and air diffusers in the newly installed ceiling tiles. ... More