Howard Thurman Center – Construction Update – 12/06/19
Week of December 9, 2019 General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking... More
CFA Renovations – Construction Update – 12/06/19
During December 6th - December 13th: (Please note that there is work scheduled for Saturday, December 7th and Sunday, December 8th) General: On Tuesday, December 10th the lower parking lot (Lot D) at 25 Buick St will be closed as a crane will be utilizing the lot to bring materials onto the lower... More
GSU Food Hall Renovations Comments/Questions
CFA Renovations – Construction Update – 11/29/19
During November 29th - December 6th: (Please note that there is work scheduled for Saturday, November 30th and Sunday, December 1st) General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the Concert Hall. Stair access directly off Commonwealth Ave... More
Geothermal Well Drilling Initiative – Construction Update – 11/29/19
During the week of December 2nd: Parking Lot N The drilling subcontractor has started drilling to depth at GT-29 and upon completion, will move on to start drilling to depth at GT-28. The site subcontractor will be handling the soil material stockpiled in the basin area for settling. The site contractor... More
Howard Thurman Center – Construction Update – 11/29/19
Week of December 2, 2019 General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking... More
Goldman School of Dental Medicine – Construction Update – 11/29/19
During the weekend of November 30: Starting at 5 a.m. on both Friday (November 29) and Saturday (November 30), crews will be replacing the existing steam heating service with a new service sized to provide heat to the existing GSDM building as well as the new north and west additions. More
Goldman School of Dental Medicine – Construction Update – 11/22/19
During the weekend of November 23: On Saturday and Sunday, work will continue throughout the interior of the seven-story west addition, with the focus on the new first-floor auditorium and student and resident lounge areas. On Saturday only, the exterior work will also continue on the north, east, and south... More
Howard Thurman Center – Construction Update – 11/22/19
Week of November 25, 2019 General: Temporary signage is posted to help the public navigate through the first floor. The main building access is through the Essex Street entrance. A secondary entrance is located on the rear of the building near the ramp to the garage. The main stairwell from the parking... More
Geothermal Well Drilling Initiative – Construction Update – 11/22/19
During the week of November 25th: Parking Lot N The drilling subcontractor has started drilling to depth at GT-6 and upon completion will move on to start drilling to depth at GT-30. The site subcontractor will be handling the soil material stockpiled in the basin area for settling. The site contractor... More