CFA Renovations – Construction Update – 1/17/20
During January 17th – January 24th: (Please note that there is work scheduled for Saturday, January 18th and Sunday, January 19th): General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the concert hall. Stair access directly off Commonwealth Ave... More
Geothermal Well Drilling Initiative – Construction Update – 1/17/20
During the week of January 20th Parking Lot N The drilling subcontractor will continue installing the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N. The site subcontractor will be installing precast concrete structures over the piping. Alleyway Construction equipment will be making periodic... More
BU Children’s Center – Construction Update – 1/16/20
During the week of January 13th On site, work includes excavating for and installing the stormwater infiltration system. Main Building Insulating of HVAC piping will occur on the 3rd floor. Installation of lights will occur on the 3rd floor. Boiler plumbing work will occur in the basement. Fire protection work will occur... More
Geothermal Well Drilling Initiative – Construction Update – 1/10/20
Parking Lot N Installation of high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N will be ongoing followed by pressure testing. Soil material stockpiling and handling in the basin area will continue. The site contractor will be using excavation equipment to remove... More
CFA Renovations – Construction Update – 1/10/20
During January 10th – January 17th: (Please note that there is work scheduled for Saturday, January 11th and Sunday, January 12th) General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the concert hall. Stair access directly off Commonwealth Ave... More
Goldman School of Dental Medicine – Construction Update – 1/10/20
During the weekend of January 11: On Saturday, work will continue throughout the interior of the seven-story west addition, with the focus on the finishing touches throughout the floors, and the continued buildout of the first-floor auditorium. Crews will also continue preparations for the concrete pour along East Newton Street... More
Geothermal Well Drilling Initiative – Construction Update – 1/6/20
Parking Lot N The drilling subcontractor will be installing the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N. Soil material stockpiling and handling in the basin area will continue. The site contractor will be using excavation equipment to remove this material... More
Goldman School of Dental Medicine – Construction Update – 1/3/20
During the weekend of January 4: On Saturday, work will continue throughout the interior of the seven-story west addition, with the focus on installing the finishing touches from all trades throughout the floors, and the continued buildout of the first-floor auditorium. During the week starting January 6: Following the removal of... More
CFA Facade, Envelope, and Accessibility Renovations – Construction Update – 1/3/20
From January 3rd through January: (Please note that there is work scheduled for Saturday, January 4 and Sunday, January 5) General: Temporary signs are posted to help direct you through the first floor. The main building access is through the west entrance near the Concert Hall. Stair access directly off Commonwealth Ave will... More
Goldman School of Dental Medicine – Construction Update – 12/27/19
During the weekend of December 28: On Saturday and Sunday, work will continue throughout the interior of the seven-story west addition, with the focus on installing flooring, mechanical and electrical devices into the ceiling gird, and casework (cabinets and counters). During the week starting December 30: Following the removal of the... More