Geothermal Well Drilling Initiative – Construction Update – 1/31/20

By Madeleine CohenJanuary 31st, 2020in Alerts, Featured Content

During the week of February 2nd: Parking Lot N The drilling subcontractor will be pressure testing the piping within the completed boreholes. Alleyway The drilling subcontractor will be pressure testing the piping within the completed boreholes. Park The drilling subcontractor will be pressure testing the piping within the completed boreholes. Construction equipment will... More

Goldman School of Dental Medicine – Construction Update – 1/31/20

By Madeleine CohenJanuary 31st, 2020in Alerts, Featured Content

During the weekend of February 1: On Sunday, night-shift work will continue, starting at 10 p.m. and continuing until 6 a.m., during which workers will be installing new telecommunications services—telephone and data communications—in the existing GSDM building; activities will include transferring the telecommunication service to connections throughout the new north... More

Geothermal Well Drilling Initiative – Construction Update – 1/24/20

By Leslie MonteiroJanuary 24th, 2020in Alerts, Featured Content

During the week of January 27th Parking Lot N The drilling subcontractor will continue installing the high-performance geothermal exchange vertical piping within the completed boreholes in the fenced in area of Lot N. The drilling subcontractor will be pressure testing the piping within the completed boreholes. Alleyway The drilling subcontractor will be... More