News
BWSC Sewerage Improvements On Beacon Street
Boston Water and Sewer Commission (BWSC) will be making improvements to the sewer system on Beacon Street. Construction will commence in the next few weeks. P. Gioiso and Sons Inc., has been contracted by BWSC to rehabilitate the sewer system in this area. The contractor will provide additional notice advising you when the work will... More
Boston University Fitness and Wellness Center @ BCYF Blackstone Now Open
BU is doing its part to combat childhood obesity, which has more than tripled in the past 30 years, according the Centers for Disease Control and Prevention. BU teamed up with the Boston Public Health Commission (BPHC) and the Boston Centers for Youth & Family (BCYF) to create a new... More
Sumner M. Redstone Building Groundbreaking Set for April 19
Celebration will mark official start of long-awaited construction project for School of Law Boston University School of Law will hold the groundbreaking ceremony for the Sumner M. Redstone Building and Law Tower renovation, the centerpiece of the School of Law's Campus Campaign, on Friday, April 19 at 2:30 pm on Alpert... More
Fire Alarm Inspection 4/22/2013 – 4/26/2013
4/22/2013 Testing all rooms and comm. area from 8am - 3pm 704, 708, 710, 714, 718, 722, 726, 728 Commonwealth Ave 4/23/2013 Testing all rooms and comm. area from 7am - 3pm 80,82 Ivy St. 85, 87 St. Mary's St. 252, 254, 258, 264 Huntington St. 4/24/2013 Testing all rooms and comm. area from 8am - More
Engineering Product Innovation Center Construction Activity for the Period of April 15 – April 19
Anticipated construction activities for the week of April 15 – April 19: 1. Site Work - The contractor has completed the installation of the new utility pipes that will go under the slab. They will be leveling the ground elevation to prepare for the new concrete slab. 2. Abatement – The... More
New Balance Field Construction Activity for the Period of April 16 – April 20
Anticipated construction activities for the week of April 16 – April 20: *The contractor will not be working on Saturday, 4/13/2013. **The contractor will not be working on Monday 4/15/2013, in observance of the Patriots Day Holiday. 1. Site Work: Already underway and continuing for the next several weeks is site... More
Fire Alarm Inspection 4/15/2013 – 4/19/2013
4/15/2013 Testing all rooms and comm. area from 8am - 3pm 141, 143, 145, 147, 226, 232, 236 Bay State Rd. 4/16/2013 Testing all rooms and comm. area from 8am - 3pm 867, 855, 853, 845 Beacon st. 25, 27 Aberdeen st. 4/17/2013 Testing all rooms and comm. area from 8am - More
Admissions Reception Center Construction 4/5/13
Other than some brick and concrete sidewalk replacement where we had been trenching in the Alpert Mall area, and final replacement of the grass surface, we are essentially now complete with the major work of the Sewer Separation Project. The next three phases of construction in the roadway area of the... More
New Balance Field Construction Activity for the Period of April 8 – April 12
Anticipated construction activities for the week of April 8 – April 12: **The contractor will be working on Saturday, 4/6/2013, beginning at 8:00am** 1. Site Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expected general construction noise... More
Engineering Product Innovation Center Construction Activity for the Period of April 8 – April 12
Anticipated construction activities for the week of April 8 – April 12: 1. Site Work - The contractor has completed the foundation for the new concrete slab. They will now begin to prepare the surface under the slab for the installation of the new utility pipes that will go... More