Fire Alarm Inspection 5/13/2013 – 5/17/2013
5/13/2013 Testing rooms from 5th fl - 11th fl 9am -3pm 700 Commonwealth Ave. Tower A, B and C 5/14/2013 Testing all rooms and comm area from 7am - 3pm 14 Buswell St. w/ BFD 9:30am 273, 275 Babcock St. 5/15/2013 Testing all rooms and comm area from 7am - 3pm 273, 275 Babcock St. 5/17/2013 Testing... More
Engineering Product Innovation Center Construction Activity for the Period of May 13 – May 17
Anticipated construction activities for the week of May 13 – May 17: **The Contractor will be working the day shift (7:30am – 3:30pm) beginning Monday, May 13 and continuing through the start of classes in September** 1. Abatement – The abatement work on the first floor of 750 Comm Ave is complete. ... More
New EPIC Studio Will Equip ENG Students with Design Skills
$18.8 million in-kind gift helps transform engineering curriculum 05.10.2013 By Leslie Friday By many accounts, manufacturing is making a comeback in the United States. US manufacturers have added 500,000 new workers since the end of 2009, energy costs have dropped, and labor costs in competing countries such as China and India have been... More
Landscaping Revs Up as Commencement Nears
Grounds crew engage in good-natured competition 05.09.2013 By Leslie Friday Everyone at BU knows that Nickerson Field is the epicenter of Commencement weekend, possibly none more than Steve Lindberg and Michael Sisti. The University grounds workers have less than two weeks to plant thousands of geraniums, petunias, and impatiens around West Campus, More
Engineering Product Innovation Center Construction Activity for the Period of May 6 – May 10
Anticipated construction activities for the week of May 6 – May 10: 1. Abatement – The contractor will continue to abate the ceiling on the first floor of 750 Comm Ave. (the old Guitar Center space). It is anticipated that the abatement will finish by the middle of the week. ... More
New Balance Field Construction Activity for the Period of May 6 – May 10
Anticipated construction activities for the week of May 6 – May 10: *The contractor WILL be working on Saturday, 5/4/2013. 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise from... More
Fire Alarm Inspection 5/6/2013 – 5/10/2013
QUIET HOURS 5/6/2013 Testing from 7am -3pm 11, 15, 19, 53, 55, 57 Deerfield St. 648, 650, 654, 656, 677 Beacon St. 5/7/2013 Testing from 7am - 3pm 25 Lenox St. pre test 8am 533 - 541, 575, 602, 985, Commonwealth Ave 100, 120 Ashford St. 300 Babcock St. 619 memorial Sr. 5/8/2013 Testing from 7am - 3pm 154, 156, More
Fire Alarm Inspection 4/29/2013 – 5/3/2013
4/29/2013 Testing rooms from 4th fl - 11th fl from 7am - 7pm 700 Commonwealth Ave Tower A, B and C 4/30/2013 Testing from 7am - 3pm 50 Buswell st 9:30am with BFD 10 Buick St. 5/1/2013 Testing from 7am - 3pm 10 Buick St. 1st and 2nd fl rooms 5/2/2013 Testing from 7am - 3pm 512, 517, More
Engineering Product Innovation Center Construction Activity for the Period of April 29 – May 3
Anticipated construction activities for the week of April 29 – May 3: 1. Site Work - The contractor will be installing insulation and a vapor barrier on the floor of the 744 Comm Ave garage in preparation for pouring the new concrete slab. 2. Abatement – The contractor will continue to abate... More
New Balance Field Construction Activity for the Period of April 29 – May 4
Anticipated construction activities for the week of April 29 – May 4: *The contractor will not be working on Saturday, 4/27/2013. 1. Site & Utility Work: Already underway and continuing for the next several weeks is site work, which includes excavators, and other earthmoving equipment. You can expect general construction noise... More