Center for Computing & Data Sciences – Construction Update – 06/24/22
During the weekend of June 25th On Saturday, crews will continue working from the elevated platforms to construct the 15th and 17th-floor soffits. Installation of the retaining wall at the rear of the Bay State Road brownstones will continue. Also on Saturday, installation of the atrium’s monumental stair and tower’s... More
Kilachand Hall Phase 2 – Construction Update – 06/17/22
Saturday, June 18th Work hours are 7 am - 3:30 pm BrandSafway will have 12-15 crew members on site erecting scaffolding along the south elevation facing Bay State Road. Consigli Construction will have staff on site for job site supervision. During the week of June 20th BrandSafway will continue with scaffold... More
Center for Computing & Data Sciences – Construction Update – 06/17/22
During the weekend of June 18th On Saturday, crews will continue working from the elevated platforms to construct the 15th-floor soffit. Installation of the retaining wall at the rear of the Bay State Road brownstones will continue. Also on Saturday, installation of the atrium’s monumental stair and tower’s communicating stair... More
Kilachand Hall Phase 2 – Construction Update – 06/10/22
Saturday, June 11th Work hours are 7 am - 3:30 pm BrandSafway will have 12 men onsite erecting scaffolding along the south elevation facing Bay State Road. Consigli Construction will also have manpower present for job site supervision. During the week of June 13th Scaffold erection to continue with the south-facing... More
Center for Computing & Data Sciences – Construction Update – 06/10/22
During the weekend of June 11th On Saturday, installation of the atrium’s monumental stair and communicating tower stair will continue. Framing, hanging, and finishing drywall will continue in the tower. Crews from the mechanical and electrical subcontractors will be on site continuing the installation of their respective systems. Polishing of the... More
Kilachand Hall Phase 2 – Construction Update – 06/03/22
During the week of June 6th The traffic management plan for the project is still being finalized with the City of Boston. In the interim, for the month of June: Four meters will be rented in front of Kilachand Hall during work hours for pre-scheduled deliveries. The accessible parking spaces... More
Center for Computing & Data Sciences – Construction Update – 06/03/22
During the weekend of June 3rd On Saturday, installation of the atrium’s monumental stair and communicating tower stair will continue. Framing, hanging, and finishing drywall will advance in the tower. Workers will continue applying fireproofing materials to the buildings steel beams and columns. Crews from the mechanical and electrical subcontractors... More
Center for Computing & Data Sciences – Construction Update – 05/27/22
During the weekend of May 28th On Saturday, installation of the atrium monumental stair will continue. Framing, hanging, and finishing drywall will advance in the tower. Workers will continue applying fireproofing materials to the buildings steel beams and columns. Crews from the mechanical and electrical subcontractors will be on site... More
Kilachand Hall Phase 2 – Construction Update – 05/27/22
During the week of May 30th The traffic management plan is being reviewed by the City of Boston. In the interim, the meters in front of Kilachand Hall will be reserved for construction as needed. The accessible parking spaces will remain in place. BU parking spots directly behind Kilachand Hall... More
Kilachand Hall Phase 2 – Construction Update – 05/20/22
During the week of May 23rd Monday, May 23rd, through the morning of Wednesday, May 25th, Residence Life and the Housing and Custodial teams will be completing move out and cleaning for the summer construction. Full site containment will begin mid-week. This will be in place for the remainder of the construction project. More