News
Kilachand Hall Phase 2 – Construction Update – 9/9/22
General Project Information Daily Work Hours from 7am-3:30pm. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and is in place. Relocated accessible parking spaces were posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey barrier site containment... More
Center for Computing & Data Sciences – Construction Update – 9/9/22
During the weekend of September 10th On Saturday, crews will be working from the elevated platforms, continuing to install panels at the 5th and 7th-floor soffits on the exterior of the building. Also on Saturday, on the interior of the building, installation of the atrium’s monumental stair and tower’s communicating... More
Kilachand Hall Phase 2 – Construction Update – 9/2/22
General Project Information Daily Work Hours are from 7 am - 3:30 pm. The approved BTD Traffic Management Plan for the project remains in place. Relocated accessible parking spaces posted for use on 6/29 (in front of 81 and 83 Bay State Road). Jersey barrier site containment in place, pedestrian... More
Center for Computing & Data Sciences – Construction Update – 9/2/22
During the weekend of September 3rd On Saturday, crews will be working from the elevated platforms continuing the installation of panels at the 5th and 7th-floor soffits on the exterior of the building. The site contractor and landscaper will continue the installation of the retaining wall, ramp, and planting beds... More
Kilachand Hall Phase 2 – Construction Update – 8/26/22
General Project Information After Friday, August 26th, the daily work hours will go back to 7 am-3:30 pm daily. The 6 am start time for any interior work will no longer be in effect. The Traffic Management Plan for the project has been approved by the Boston Transportation Department and... More
Center for Computing & Data Sciences – Construction Update – 8/26/22
During the weekend of August 27th On Saturday, crews will be working from the elevated platforms continuing the installation of panels at the 5th and 7th-floor soffits on the exterior of the building. The site contractor and landscaper will continue the installation of the retaining wall, ramp, and planting beds... More
Kilachand Hall Phase 2 – Construction Update – 8/19/22
General Project Information After Friday, August 26th, the daily work hours will go back to 7 am - 3:30 pm daily. The 6 am start time for any interior work will no longer be in effect. The Traffic Management Plan for the project has been approved by the Boston Transportation... More
Center for Computing & Data Sciences – Construction Update – 8/19/22
Upcoming Crane work at the Center for Computing & Data Sciences during the weekend of August 20th to impact access to/from area parking lots and roadways As part of the ongoing construction, Granby Street will be closed on August 20th and 21st to enable a large mobile crane to be... More
Kilachand Hall Phase 2 – Construction Update – 8/12/22
General Project Information Daily project work hours have been adjusted as of the week of 7/11: Now 6 am-3:30 pm for interior work Remains 7 am-3:30 pm for exterior work The Traffic Management Plan for the project has been approved by the Boston Transportation Department. (Implementation of plan underway this... More
Center for Computing & Data Sciences – Construction Update – 8/12/22
During the weekend of August 13th On Saturday, crews will be working on the exterior of the building from the elevated platforms to continue installing panels at the 5th and 17th-floor soffits. The site contractor and landscaper will continue the installation of the retaining wall, ramp, and planting beds between... More