Myles Standish Hall – Saturday Work – 5/19/18
Onsite Construction Clean up and loadout Interior work Exterior Site work
Myles Standish Hall – Saturday Work – 5/12/18
Onsite Construction Saturday Work – 5/12/18 Clean up and loadout Interior work millwork
Goldman School of Dental Medicine – Construction Update – 5/4/18
During the week of May 7: Demolition of and removal of debris from the roof and first floor walls of […]
Myles Standish Hall – Saturday Work – 5/5/18
Onsite Construction Clean up and loadout Interior work – millwork
Goldman School of Dental Medicine – Construction Update – 4/27/18
During the week of April 30: On Thursday, April 26, the newly installed handicap lift at the East Newton Street […]
Myles Standish Hall – Construction Activity – For 4/28/18 to 5/4/18
For 4/28/18 to 5/4/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 4/28/18
Onsite Construction Clean up and loadout Interior work millwork
Goldman School of Dental Medicine – Construction Update -4/20/18
During the week of April 23: Demolition will continue in the GSDM cafeteria’s basement, including hazardous material abatement under protocols […]
Myles Standish Hall – Construction Activity – For 4/21/18 to 4/27/18:
For 4/21/18 to 4/27/18: Deliveries – Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both […]
Myles Standish Hall – Saturday Work – 4/21/18
Onsite Construction Clean up and loadout Interior work Install curtainwall Beacon Street