Goldman School of Dental Medicine – Construction Update – 7/27/18
During the weekend of July 28: Utility work on Albany Street, from the GSDM building to 650 Albany Street, will […]
Myles Standish Hall – Construction Update – 7/26/18
For 7/28/18 to 8/3/18: On-site Construction Saturday Work – 7/28/18 – 7 am to 5 pm Clean up and load […]
Myles Standish Hall – Saturday Work – 7/28/18
On-site Construction Clean up and load out Annex interior demo and load out Annex exterior work
Goldman School of Dental Medicine – Construction Update – 7/20/18
During the weekend of July 21: Utility work on Albany Street, from the GSDM building to 650 Albany Street, will […]
Myles Standish Hall – Construction Update – 7/20/18
For 7/21/18 to 7/27/18: Deliveries – Subcontractors will receive deliveries all week between 7 am and 6 pm on both Beacon […]
Myles Standish Hall – Raleigh Street Water Work – 7/19/18
Thursday 7/19/18 Flett will be working in Raleigh Street to cut and cap existing water feeds to Annex from 2 […]
Myles Standish Hall – Construction Update – 7/21/18
On-site Construction Clean up and load out Annex interior demo and load out Annex exterior work
Myles Standish Hall – Construction Update – 7/13/18
For 7/14/18 to 7/21/18: Deliveries – Subcontractors will receive deliveries all week between 7 am and 6 pm on both Beacon […]
Goldman School of Dental Medicine – Construction Update – 7/13/18
During the weekend of July 14: Utility work on Albany Street, from the GSDM building to 650 Albany Street, will […]
Summertime, and the Construction Is Ongoing
Among the 31 projects: an improved Alumni Center, apartment renovations, new labs