Myles Standish Hall – Construction Update – 7/26/18
For 7/28/18 to 8/3/18:
On-site Construction
Saturday Work – 7/28/18 – 7 am to 5 pm
- Clean up and load out
- Interior Work – Myles
- Annex interior framing and MEP roughs
- Annex exterior façade work
- Annex set curb Raleigh Street
Myles – 7 am to 6 pm
Load out
- Load out at Beacon Street and Bay State Road – Load out debris from 1st floor to dumpsters with ongoing daily dumpster swaps.
Site
- Myles
- Bay State Road – Continue with cut and caps in Bay State Road
- Bay State Road and Beacon Street
- Continue with installation of pavers and landscape
Annex – 7 am to 6 pm
Load out
- Load out at Bay State Road and Beacon Street to dumpsters with ongoing daily dumpster swaps.
Roof
- Masonry restoration
- Roof terminations, flashings, and masonry
Masonry Restoration
- Beacon Street, Raleigh Street, and Bay State Road continue with façade restoration