Center for Computing & Data Sciences – Construction Update – 9/4/20
During the weekend of September 5th On Saturday, crews will be on site to continue with the installation of cross […]
Goldman School of Dental Medicine – Construction Update – 9/2/20
Please Note: Special update for Thursday, September 3: The GSDM Project Team has been notified that there will be a […]
Center for Computing & Data Sciences – Construction Update – 8/28/20
During the week of August 31st Excavation for the building foundations continues. The first cut (down roughly eight feet from […]
CFA Renovations – Construction Update – 8/28/20
For the period of August 28th – September 4th: South Façade Painting of the alcove at the center entrance on […]
Goldman School of Dental Medicine – Construction Update – 8/28/20
During the weekend of August 29: On Saturday, a small work crew will be installing the mounting plates and support […]
Goldman School of Dental Medicine – Construction Update – 8/21/20
During the weekend of August 22: A small crew of carpenters will continue working in the GSDM building during the […]
Center for Computing & Data Sciences – Construction Update – 8/21/20
During the weekend of August 22nd On Saturday crews will be on site to continue with the installation of cross […]
CFA Renovations – Construction Update – 8/21/20
For the period of August 21st – August 28th: Please note that there is work scheduled for this weekend Saturday, […]
Center for Computing & Data Sciences – Construction Update – 8/14/20
During the week of August 17th Excavation for the building foundations continues. The first cut (down roughly eight feet from […]
CFA Renovations – Construction Update – 8/14/20
For the period of August 13th – August 21st: Please note that there is work scheduled for this weekend Saturday, […]