CFA Renovations – Construction Update – 8/28/20

For the period of August 28th – September 4th:
South Façade
- Painting of the alcove at the center entrance on Commonwealth Avenue will begin.
North Façade
- Relieving angles and brick installation on the lower level will continue.
- Work rebuilding the east chimney will continue.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!