Category: Alerts
Kilachand Hall Phase 2 – Construction Update – 4/14/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 4/14/23
Project Updates The drywall installation in the Residence Life offices is expected to be completed this Saturday, 4/15. The electrical […]
West Campus Dining Expansion – Construction Update – 4/7/23
Project Updates The contractor is nearing the completion of the sheetrock installation and the mechanical rough-in work. Sheetrock tapping has begun. […]
Kilachand Hall Phase 2 – Construction Update – 4/7/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
Kilachand Hall Phase 2 – Construction Update – 3/31/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 3/31/23
Project Updates Contractor began the installation of sheetrock following the rough-in inspection and sign off. Work on the overhead mechanical […]
West Campus Dining Expansion – Construction Update – 03/24/23
Interior Work Last week, the electrical rough-in work was completed and inspected. The metal stud framing was also completed and is […]
Kilachand Hall Phase 2 – Construction Update – 03/24/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]
West Campus Dining Expansion – Construction Update – 03/17/23
General Project Updates The past week consisted of metal stud framing, rough electrical and ductwork, and piping for HVAC in the […]
Kilachand Hall Phase 2 – Construction Update – 03/17/23
General Project Information Daily Work Hours from 7 am – 3 pm. The Traffic Management Plan for the project has […]