Interior Work

  • Last week, the electrical rough-in work was completed and inspected.
  • The metal stud framing was also completed and is set to be inspected early next week, the week of March 27.
  • Installation of drywall will begin once the inspection is passed.
  • Installation of the HVAC ductwork will continue.

Exterior Work

  • The demolition of the curbed brick wall has been completed.
  • Installation of concrete for the footing at the new canopy is tentatively scheduled for Wednesday, March 29. Once confirmed, a concrete truck will be on site to pour the footing. Police detail will be on site during this activity.
  • Dumpster exchange is scheduled for Friday, March 31.