Myles Standish Hall – Construction Activity – 10/8/16 to 10/14/16
Monday – 10/10/16 – No work due to Columbus Day. For the rest of the week the following work will take place: Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
Myles Standish Hall – Saturday Work – 10/08/16
On Saturday, the following construction work will be occurring onsite from 7am – 5pm. Activities will require workers, trucks, and equipment in point park area.
Myles Standish Hall – Construction Activity – 10/1/16-10/7/16
Subcontractors will receive deliveries all week from 7 a.m. until 6 p.m. on both Beacon Street and Bay State Road. Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
CILSE – Construction Activity – Week of 10/2/16
Waterproofing of the air-vapor barrier (AVB) on the notch on the Morse Auditorium side of the building will take place, as well as rainscreen installation using mast climber 5. AVB installation will continue on the first and second floors below mast climber 5.
Myles Standish Hall – Saturday Work – 10/1/16
Install of relieving angles in the alley on fraco. Clean and stock staging for masons in the alley and on the Beacon Street and Bay State Road sides of building. Interior rough and interior demolition. Activities will require workers, trucks, and equipment in point park area.
CILSE – Construction Activity – Week of 9/25/16
Glazing, rainscreen installation, and air-vapor barrier waterproofing will take place on the on the notch on the Morse Auditorium side of the building using mast climber 5. Installation of rainscreen will continue on the connector bridge and from the 3rd floor down on the Cummington Mall side.
Myles Standish Hall – Construction Activity – 9/24/16 – 9/30/16
Subcontractors will receive deliveries all week from 7 a.m. to 6 p.m. on both Beacon Street and Bay State Road. Beacon Street Work – 9/12/16 through 09/27/16 – The following construction work will be occurring on Beacon Street from 9:30 a.m. to 3:30 p.m.
BU Theatre Center – Construction Activity – 9/24/16 – 10/15/16
The project team will hold a meeting to present details of the project program and design and to inform the BU community of the project’s progress on Wednesday, September 28 at 3:30 p.m. in room 110 at 928 Commonwealth Avenue (SHA).
Myles Standish Hall – Construction Activity – 9/17/16 to 9/23/16
Saturday, 9/17/16 – No work. Beacon Street Work – 9/12/16 through 9/27/16 – Starting on Tuesday, September 6th, the following construction work will be occurring on Beacon Street from 9:30 a.m. until 3:30 p.m.
CILSE – Construction Activity – Week of 9/18/16
Mast climber 5 will be in operation, and the notch on the Morse Auditorium side of the building will continue to get enclosed. Installation of rain screen will continue on the connector bridge and from the third floor down on the Cummington Mall side.