Center for Computing & Data Sciences – Construction Update – 7/17/20
During the week of July 20th Installation of mini piles will continue; this activity will be working east to west […]
Goldman School of Dental Medicine – Construction Update – 7/17/20
During the weekend of July 18: On Saturday, East Newton Street will be temporarily closed to traffic while workers set […]
CFA Renovations – Construction Update – 7/17/20
For the period of July 17th – July 24th: General: The west alley entrance will remain closed over the next […]
Student Packing Program
Custodial Operations, Vending Services, Housing, and Emergency Management have been working together on the unique student move-out process this year. Trucking […]
Goldman School of Dental Medicine – Construction Update – 7/10/20
During the weekend of July 11: On Saturday, plumbing crews will be working inside the GSDM building, creating coring holes […]
Center for Computing & Data Sciences – Construction Update – 7/10/20
During the week of July 13th Driving of the sheeting for the Support of Excavation (SOE) system will continue along […]
CFA Renovations – Construction Update – 7/10/20
For the period of July 10th – July 17th: General: The west alley entrance will remain closed over the next […]
StuVi2 Is Getting Ready to Shine Like Never Before
Tim O’Connor, Electrical Services Manager at FMO, is leading the massive electrical lighting upgrade project at 33 Harry Agganis Way. Nearly […]
Goldman School of Dental Medicine – Construction Update – 7/2/20
During the weekend of July 4: There will be no work on the GSDM site this weekend. During the week […]
Center for Computing & Data Sciences – Construction Update – 7/2/20
During the week of July 6th Driving of the sheeting for the Support of Excavation (SOE) system will continue along […]