Author: Leslie Monteiro
CFA Renovations – Construction Update – 7/2/20
For the period of July 3rd – July 10th: General: The west alley entrance will remain closed over the next […]
Center for Computing & Data Sciences – Construction Update – 6/26/20
During the week of June 29th Installation of utility feeds, power, and water from Granby Street to the site will […]
CFA Renovations – Construction Update – 6/26/20
For the period of June 26th – July 3rd: General: The west alley entrance will remain closed over the next […]
Goldman School of Dental Medicine – Construction Update – 6/26/20
During the weekend of June 27: On Saturday, the fire protection system will be shut down from 5 a.m. to […]
Goldman School of Dental Medicine – Construction Update – 6/19/20
During the weekend of June 20: On Saturday, crews will continue with the removal of hazardous material from the phase […]
Center for Computing & Data Sciences – Construction Update – 6/19/20
During the week of June 22nd Installation of utility feeds from Granby St. to the site will continue. Driving of […]
CFA Renovations – Construction Update – 6/19/20
For the period of June 19th – June 26th: General: The west alley entrance will remain closed over the next […]
Goldman School of Dental Medicine – Construction Update – 6/12/20
During the weekend of June 13: On Saturday, crews will continue with hazardous material removal from areas being demolished within […]
Center for Computing & Data Sciences – Construction Update – 6/12/20
During the week of June 15th Installation of monitoring points for utilities will continue. Excavation within the perimeter of the […]
CFA Renovations – Construction Update – 6/12/20
For the period of June 12th – June 19th: General: The west alley entrance will remain closed over the next […]