Center for Computing & Data Sciences – Construction Update – 01/13/23

During the weekend of January 14th

  • On Saturday, crews will be on site delivering and assembling furniture.
  • On Saturday and Sunday, crews will be wrapping up work in the atrium and Stair D and removing the temporary protection.

During the week of January 16th

  • Crews will be on site on Monday, January 16 to continue assembling furniture and preparing for classes.
  • Crews will continue addressing punch list items throughout.
  • Start-up, testing, and commissioning of the building’s systems continues.
  • Installation of AV equipment in the classrooms and conference rooms will continue.
  • Exterior site work continues. Crews will begin installing granite pavers at the Granby Street and Bay State Road park.
  • Assembly of the bike shelter located between the building and Sargent College will continue.
  • Deliveries and assembly of office furniture will continue.