BU Children’s Center – Construction Update – 8/16/19

During the week of August 19th

  • Site
    • Excavate for and install stormwater infiltration system
  • Utilities
    • Install gas line and meter
  • Pluming
    • UG plumbing at play support building
  • Concrete
    • Prep and pour for SOG
  • Framing
    • Stair #1 framing

During the week of August 26th

  • Site
    • Excavate for and install stormwater infiltration system
  • Plumbing
    • UG plumbing at main building
  • Framing
    • Connector framing

As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered. Your safety is imperative!