Warren Towers Construction Update – 7/3/26

General Project Information

  • Warren Towers Dining Hall, Offices, Student Rooms, Parking Garage (Lot K), and Bike Storage Room are now closed for the summer.
  • Weekday and weekend shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). 
  • Entering the jobsite: Authorized personnel only and no trespassing. Anyone wishing to enter the site must sign in at the construction office, observe and comply with all posted signage and personnel protective equipment requirements.
  • Emergency Contacts:
    • Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 7/4/26

The site is closed on July 4th

Saturday & Sunday (1st, 2nd & 3rd shift)

Exterior Work

Tower A

  • Crews continue disassembling staging.
  • Work continues in the new Mechanical Penthouse and Emergency Electrical Room.
Pictured is the mechanical pipe insulation.
  • Mechanical equipment startup is underway.

      Tower B

      • Electricians are installing temporary power and lighting.
      • Masonry restoration and brick cleaning continue.
      • Exterior window abatement and demolition are ongoing.
      • Demolition of parapet, mechanical penthouse, and insulated pavers on the upper roof continues.

        Tower C

        • Metal tie-back hardware will be installed for swing staging.

        Podium Roofs

        • Construction of new masonry parapets.
        • Demolition of existing roofing systems, mechanical equipment, penthouses, and skylights is in progress.
        • Installation of new mechanical equipment and penthouse continues.
        • Work on staging and support steel for Tower C continues.
        • Installation of new roofing systems and parapets is underway.
        • Heat pump, condenser, piping, and electrical installations continue.
        • Work on the acoustic roof screen and the new boiler room is ongoing.

            Commonwealth Ave. 

              • Curtainwall window replacement on level 4.

                  Cummington Mall
                  In and around the fenced area.

                    • Installation of Tower C hoist way foundation and mini pile. 
                    • Two cranes will be set up separately in the street to support podium B roof activities and hoist the bridge beams off Tower A. 
                    • Daily deliveries of construction materials and loading out of demolition debris dumpsters.
                    • Two-car personnel and materials hoist way remains in operation.
                      • (The elevator operators begin their safety checks and preventative maintenance on the hoist way daily at 6:00 AM)

                        Cummington Mall West

                        • A crane will be set up in the street to support podium D roof activities and west terraces.
                        • Please watch for sidewalk closures, BUPD detail officers, cones, and observe signage. 

                        Hinsdale Mall

                        • A crane will be set up in the street to support podium A roof activities.
                        • Please watch for sidewalk closures, BUPD detail officers, cones, and observe signage. 

                          Interior Work

                          Main Entrance Lobby

                          • Escalator replacement in progress.

                          Tower A

                            • Interior final cleaning and air and water balancing are ongoing.
                            • Punch list items and touchups are ongoing.

                              Tower B

                              • Crews are making safe exiting of MEP, F/P systems.
                              • Demolition of the abatement is in progress.

                                Tower C

                                • Corridor flooring abatement continues.
                                • Installation of staging tieback hardware and covers continues.

                                  Dining Hall

                                  Pictured is the wall and ceiling tile in the Dining Hall.
                                  • Installation of drywall and cement board continues.
                                  • New rough plumbing, electrical, HVAC, and fire protection sprinkler.
                                  • Waterproofing and tile installation work is underway.
                                  • The Dining Hall Renovation work is planned for 3 shifts, 7 Days a week until opening in the fall.
                                  Pictured is the concrete floor infill.
                                  Pictured is the concrete pump truck.

                                        Parking Garage

                                        • Dining hall freight elevator modernization continues.
                                        • Electrical, plumbing, mechanical piping, and sprinkler installations are ongoing.
                                        • Construction of the main fire pump room and MDF room continues.
                                        • Concrete and structural steel repairs in the parking garage are underway.
                                        Pictured are the parking garage repairs.

                                        • Masons are installing block walls in the new mechanical and electrical rooms.

                                                    During the week of 7/6/26

                                                    Crews working 1st, 2nd & 3rd shifts

                                                    Exterior Work

                                                    Tower A

                                                      Pictured is the progress of Tower A east.
                                                      • Crews continue disassembling staging and access bridges.
                                                      • Masonry touchups and punch list work are ongoing.
                                                      • Work continues in the new Mechanical Penthouse and Emergency Electrical Room.

                                                          Tower B

                                                          • Electricians are installing temporary power and lighting.
                                                          • Masonry restoration and brick cleaning continue.
                                                          • Exterior window abatement and demolition are ongoing.
                                                          • Demolition of parapet, mechanical penthouse, and insulated pavers on the upper roof continues.

                                                            Tower C

                                                            • Metal tie-back hardware will be installed for swing staging.

                                                            Podium Roofs

                                                            • Construction of new masonry parapets.
                                                            • Demolition of existing roofing systems, mechanical equipment, penthouses, and skylights is in progress.
                                                            Pictured is the progress of the skylight curb on Podium B roof.
                                                            • Installation of new mechanical equipment and penthouse continues.
                                                            • Work on staging and support steel for Tower C continues.
                                                            • Installation of new roofing systems and parapets is underway.
                                                            • Heat pump, condenser, piping, and electrical installations continue.
                                                            • Work on the acoustic roof screen and the new boiler room is ongoing.

                                                                Commonwealth Ave. 

                                                                  • Curtainwall window replacement on level 4.

                                                                      Cummington Mall
                                                                      In and around the fenced area.

                                                                        • Installation of Tower C hoist way foundation and mini pile. 
                                                                        • Two cranes will be set up separately in the street to support podium B roof activities and hoist the bridge beams off Tower A. 
                                                                        • Daily deliveries of construction materials and loading out of demolition debris dumpsters.
                                                                        • Two-car personnel and materials hoist way remains in operation.
                                                                          • (The elevator operators begin their safety checks and preventative maintenance on the hoist way daily at 6:00 AM)

                                                                            Cummington Mall West

                                                                            • A crane will be set up in the street to support podium D roof activities and west terraces.
                                                                            • Please watch for sidewalk closures, BUPD detail officers, cones, and observe signage. 

                                                                            Hinsdale Mall

                                                                            • A crane will be set up in the street to support podium A roof activities.
                                                                            Pictured is the crane on Hinsdale Mall.
                                                                            • Please watch for sidewalk closures, BUPD detail officers, cones, and observe signage. 

                                                                              Interior Work

                                                                              Main Entrance Lobby

                                                                              • Escalator replacement in progress.
                                                                              Pictured is the progress of the escalator.

                                                                              Tower A

                                                                              • Stairwell handrail alterations and flooring install is ongoing.
                                                                              • Flooring installation, painting, and corridor wall tile work continue.
                                                                              • Installation of countertops, windowsills, wall panels, mirrors, and window treatments is ongoing.
                                                                              • Interior final cleaning, air and water balancing, and mechanical system startup, testing, and commissioning continue.
                                                                              • Punch list items and design team touchups are ongoing throughout the building.

                                                                                    Tower B

                                                                                    • Crews are making safe exiting of MEP, F/P systems.
                                                                                    Pictured are the mechanicals feeding in Tower B.
                                                                                    • Installation of temporary lighting and fire alarm.
                                                                                    • Demolition of the abatement is in progress.

                                                                                    Tower C

                                                                                    • Corridor flooring abatement continues.
                                                                                    • Installation of staging tieback hardware and covers continues.

                                                                                      Dining Hall

                                                                                      • Structural steel installation continues.
                                                                                      • Installation of drywall and cement board continues.
                                                                                      • Waterproofing and tile installation work is underway.
                                                                                      Pictured is the waterproofing and tile of the Dining Hall.
                                                                                      • Construction of new restroom/locker rooms.
                                                                                      Pictured is the prefabricated plumbing for the new bathrooms.
                                                                                      • The Dining Hall Renovation work is planned for 3 shifts, 7 Days a week until opening in the fall.

                                                                                              Parking Garage

                                                                                              • Dining hall freight elevator modernization continues.
                                                                                              • Electrical, plumbing, mechanical piping, and sprinkler installations are ongoing.
                                                                                              Pictured are the mechanical pipes.
                                                                                              • Construction of the main fire pump room and MDF room continues.
                                                                                              • Concrete and structural steel repairs in the parking garage are underway.
                                                                                              • Masons are installing block walls in the new mechanical and electrical rooms.

                                                                                                        Future / Notable Tasks

                                                                                                        • Upcoming inspections include the fire pump and final Tower A inspections for electrical, generator, plumbing, mechanical, fire alarm, building, and elevator systems.
                                                                                                        • Utility work continues on Commonwealth Avenue.