Warren Towers Renovation Construction Update – 3/27/26

General Project Information

  • Weekday shifts run from 7:00 a.m. to 3:30 p.m. (1st shift), 9:00 a.m. to 5:00 p.m. (1st shift for work outside/adjacent to student rooms), 3:00 p.m. to 11:00 p.m. (2nd shift), and 11:00 p.m. to 7:00 a.m. (3rd shift). Weekend shifts operate from 7:00 a.m. to 5:00 p.m.
  • The team is currently in the main renovation phase of the project.
  • Entering the jobsite: Authorized personnel only & no trespassing. Anyone wishing to enter the site must sign in at the construction office, observe and comply with all posted signage and personnel protective equipment requirements.
  • Emergency Contacts:
    • Owner’s Representative – Leftfield Project Management: Corey Davidson – 508-330-8489
    • Contractor Representative – Shawmut Design & Construction: Matt Galloway – 617-413-7758

During the Weekend of 3/28

Thursday 3/36 & Friday 3/27 work was postponed

Saturday & Sunday (1st and 2nd shift)

Exterior Work

Tower A

4th Floor Podium Roofs

  • Low roofs will be used as laydown areas for tools, supplies, and materials as the staging is getting disassembled.
  • Staging crews will be removing their material from the lower roof levels using a mobile crane.

East & West Facades

  • Sealing and caulking of windows and metal trim panels.
  • Masons are working on punch list items and touchups identified by the design team.

Front Façade and on Commonwealth Avenue

  • Sealing and caulking of windows and metal trim panels.
  • Masons are working on punch list items and touchups identified by the design team.
  • Installation of new door opening on the sidewalk at the fire pump room.

Rear Façade and Back Alley

  • Steel stud framing of window openings and closing of the building access leave out sections.
  • Installation of windows and metal trim along with caulking.
  • Masons will continue with exterior brick veneer restoration work, selective demolition, installation of restoration anchors, air, water, and vapor barriers, new lintels, flashings, and relieving angles.
  • Disassembly of the hoist way access bridge.

Upper Roof

  • Work on the emergency backup generator connections continues.
  • Work continues on constructing the new mechanical penthouse and emergency electric room.
  • Assembly and installation of the DOAS unit, piping, sheet metal ductwork, and electrical connections continue.
  • Installation of metal panel roof screen.

      Tower B

      North, South, East, and West Facades

      • Staging crews will continue assembling scaffolding on levels 5 through 18.
      Pictured is the staging at Tower B’s roof top.

      West Podium Terrace

      • Assembly and installation of heat pumps and condensers, including piping and electrical connections, continues on the mechanical platform.
      • Carpenters are working on the acoustic roof screen assembly.

      Multipurpose Room Roof (Podium D)

      • Work continues on constructing the new boiler room.
      • Installation of new roofing system and parapets.

      Cummington Mall
      (In and around the fenced area)

      • Daily deliveries of tools, supplies, and materials will be received at the construction loading docks within the fenced area.
      • Two-car personnel and materials hoist way remains in operation.
        • (The elevator operators begin their safety checks and preventative maintenance on the hoistway daily at 6:00 AM)
      • Tower B hoist way bridge construction is ongoing.

      Cummington Mall West

      • BUPD detail officers and construction staff will be on-site to assist with pedestrian and vehicular traffic.

      Hinsdale Mall

      • Crews are installing scaffolding on the east end of the building.
      • Warren Towers garage (lot K) will remain open.
      • Please watch for sidewalk closures, BUPD detail officers, cones, and observe signage.

        Interior Work

        Tower A

        Pictured is the furniture test fit.
        Pictured is another view of the furniture fit.
        • Rough-in of HVAC piping, electrical, fire alarm, plumbing, and sheet-metal ductwork is ongoing.
        • Pressure testing of mechanical piping and sheet metal ductwork.
        • Steel stud framing of interior partitions and soffits.
        • Installation of hollow metal door frames.
        • Application of spray fireproofing, expanding foam insulation, and firestopping continues.
        • New window installation continues.
        • Drywall installation and taping.
        • Plaster patching at columns and beams continues.
        • Stair handrail and riser alterations.
        • Prime and painting of walls, ceilings, soffits, doors, and door frames.
        • Floor preparation, waterproofing, and tile installation are ongoing in the core bathrooms.
        • Flooring and base installations in student dorm rooms.
        • Wall tile installation in corridors.
        • Installation of doors, hardware, and millwork.
        • Installation of solid surface countertops, windowsills, and hand drier panels.
        • Modernization of the tower elevators by Otis Elevator Company continues Saturdays and Sundays.
        • Finalization of plumbing, electrical and mechanical.

                Dining Hall

                • Crews will be making drain connections.

                  Parking Garage 

                  • Work continues in main electrical room.
                  • Electricians will continue running wiring, conduits, and electrical gear throughout the parking garage, 1st, 2nd, and 3rd levels.
                  • Installation and assembly of electrical gear continues.
                  • Plumbers are installing new water and drain lines in the basement, 1st, 2nd, and 3rd levels.
                  Pictured is the grease trap.
                  • Installation of mechanical piping continues.
                  • Construction of the new fuel storage room is ongoing in the southeast basement level of the parking garage.
                  • MDF room construction continues.
                  Pictured is the fiber optic cabling in MDF room
                  • Concrete and steel structural repair work continues in the parking garage on the 1st, 2nd, and 3rd floors.
                  • Sprinkler work continues on all levels.
                  Pictured is the sprinkler drain down assembly.
                  • Masons continue installing block walls in the new mechanical and electrical rooms.
                  • Operation of temporary heaters on level 3.
                  • Please watch for adjusted parking patterns, cones, and observe signage.

                          During the week of 3/30

                           Crews working 1st, 2nd & 3rd shifts

                          Exterior Work

                          Tower A

                          4th Floor Podium Roofs

                          • Low roofs will be used as lay down areas for tools, supplies, materials as the staging is getting disassembled.
                          • Staging crews will be removing their material off of the lower roof levels using a mobile crane.

                          East & West Facades

                          • Sealing and caulking of metal panels and windows continues.
                          • Masons are working on punch list items and touchups identified by the design team.

                          Front Façade and on Commonwealth Avenue

                          • Sealing and caulking of metal panels and windows continues.
                          • Masons are working on punch list items and touchups identified by the design team.
                          • Installation of new door opening on the sidewalk at the fire pump room on the street level.

                          Rear Façade and Back Alley

                          • Steel stud framing of window openings and closing up of the building access leave out sections.
                          • Installation of windows and metal trim, along with caulking.
                          • Masons will continue exterior brick veneer restoration work, including selective demolition and installation of restoration anchors, air-, water-, and vapor-barrier systems, new lintels, flashings, and relieving angles.
                          • Disassembly of the hoist way access bridge.

                          Upper Roof

                          • Work continues constructing the mechanical penthouse and emergency electric room.
                          • Assembly and installation of DOAS units, piping, sheet metal ductwork, and electrical connections continue.
                          • Work on the emergency generator connections continues.
                          • Installation of metal panel roof screen.

                            Tower B

                            North, South, East, and West Facades

                            • Scaffolding installation continues on all façades.

                            West Podium Terrace

                            • Assembly and installation of heat pumps and condensers continue, along with piping and electrical connections.
                            • Carpenters will be working on the roof screen assembly.
                            Pictured is the air water vapor barrier in screen wall.

                              Multipurpose Room Roof (Podium D)

                              • Work continues constructing the new boiler room.
                              • Installation of new roofing system and parapets.

                              Cummington Mall
                              (In and around the fenced area)

                              • Daily deliveries of tools, supplies, and materials will continue.
                              • Two-car personnel and materials hoist way remains in operation.
                                • (Elevator operators begin daily safety checks and preventative maintenance at 6:00 a.m.).
                              • Temporary elevator hoist way and bridge beam assembly for Tower B continues and impacts two entry/exit doors at 111 Cummington Mall.

                              Cummington Mall West

                              • BUPD detail officers and construction staff will be on-site.

                              Hinsdale Mall

                              • Crews are installing scaffolding on the east end of the building.
                              • Watch for sidewalk closures, BUPD detail officers, cones, and observe signage.

                              Interior Work

                              Tower A

                              • Rough-in of HVAC piping, electrical, fire alarm, plumbing and sheet metal ductwork is ongoing.
                              • Pressure testing of mechanical piping and sheet metal ductwork continues.
                              • Steel stud framing of interior partitions and soffits continues.
                              • Installation of hollow metal door frames continues.
                              • Fireproofing and firestopping continues.
                              • New window installation continues.
                              • Drywall installation and taping continue.
                              • Plaster patching continues.
                              • Stair handrail and riser alterations continue.
                              • Priming and painting of walls, ceilings, soffits, doors, and door frames continues.
                              • Floor preparation, waterproofing, and tile installation is ongoing in the core bathrooms.
                              • Flooring and base installation begins in the student dorm rooms.
                              • Wall tile installation in the corridors begins.
                              • Installation of doors and hardware, and millwork begins.
                              • Installation of solid surface countertops, windowsills, and hand drier panels.
                              • Otis elevator modernization continues.
                              • Finalization of plumbing, electrical, and mechanical.
                              • Third-party inspectors remain onsite as needed.

                                          Dining Hall

                                          • Crews will be making drain connections.

                                            Parking Garage

                                            • Work continues in the main electrical room.
                                            • Electricians will continue running wiring and conduits throughout the parking garage on levels 1 through 3.
                                            • Installation of electrical gear continues.
                                            • Plumbers will continue installing new water and drain lines in the basement and levels 1 through 3.
                                            • Mechanical piping installation continues.
                                            • Fuel storage room construction continues.
                                            • MDF room construction continues.
                                            • Concrete and steel structural repair work continues on levels 1 through 3.
                                            Pictured is the concrete repair area.
                                            • Work on sprinklers continues.
                                            • Masons will continue installing block walls in the new mechanical and electric rooms.
                                            Pictured is the mechanical room.
                                            • Temporary heaters remain in operation on Level 3.
                                            • Please watch for adjusted parking patterns, BUPD detail officers, cones, and observe signage.

                                                        Future / Notable Tasks

                                                        • Continue performing FM global roof uplift testing on all roofs.
                                                        • Tower A – 3rd state elevator inspection.
                                                        • Fire pump delivery to the site in April.
                                                        • 1st furniture delivery 4/9.
                                                        • Dining hall renovation begins on 5/9.
                                                        • Escalator replacement starts on 5/19.