Center for Computing & Data Sciences – Construction Update – 9/25/20

Excavation and installation of SOE cross bracing continues

During the weekend of September 26th

  • On Saturday, crews will be on-site to continue with excavation in the tower portion of the building, along with the installation of bracing for the support of the excavation system.

During the week of September 28th

  • The project team has revised the logistics for the large concrete pour of the podium mat slab scheduled for this Thursday, October 1st. The modified plan will now have concrete trucks utilizing the construction gate off Granby Street for site access, instead of the alley along Silber Way. Trucks will also be entering the site via the construction gate on the corner of Commonwealth Avenue and Granby Street as originally planned. This activity will involve approximately 120 trucks entering and exiting the site starting at 7 am and is anticipated to be completed around 8 pm. For additional information and logistic plans for this upcoming activity, click here.
  • Please be aware of all directional signage, as pedestrian travel paths may be altered.
  • We will continue to provide you with up to date information via these notifications.
Ongoing rebar installation for the podium’s structural mat slab

View all posts