Center for Computing & Data Sciences – Construction Update – 6/5/20
During the week of June 8th
Sidewalk protection and pedestrian barriers will be placed in the parking lane as preparations begin to shift the sidewalk for the duration of construction.
Installation of monitoring points for utilities will occur.
Excavation within the perimeter of the site for installation of the support of excavation system will continue.
Installation of utility feeds from Granby Street to the site will begin.
As activity in and around the site begins to increase, please be aware of all directional signage, as pedestrian travel paths may be altered.
We will continue to provide you with up to date information via these notifications.
Surcharge material will remain in place through the end of June.