During August 30th – September 6th:
On the Ground Level
- Work will continue along Corridor B93 as well as on the rooms along the corridor on the exterior side (south).
On the 1st Level
- The installation of HVAC piping and ductwork will continue in Corridor 197.
- Work will continue in the Commonwealth Gallery with the installation of HVAC equipment, sprinkler work and ceiling grid.
- The elevator lobby will have ongoing work with the installation of HVAC equipment, lighting, and ceiling work.
- Work will commence in Class Lab 109 as ductwork and HVAC pipe begin installation.
On the 2nd Level
- Work will continue in the restrooms aiming for completion in the next week.
On the 4th Level
- Demolition will continue in the restrooms with the intent to begin framing in the next few days.
As a reminder to all, please be aware of all directional signage, as pedestrian travel paths may be altered at both the interior and exterior of the building. Your safety is imperative!