For 8/11/18 to 8/17/18:
Deliveries
- Subcontractors will receive deliveries all week between 7 am and 6 pm on both Beacon Street and Bay State Road
On-site Construction
Saturday Work – 8/11/18 – 7 am to 5 pm
- Annex fire alarm inspection
- Landscaping
Myles – 7 am to 6 pm
Load out
- Load out at Beacon Street and Bay State Road – Load out debris from 1st floor to dumpsters with ongoing daily dumpster swaps
Site
- Myles
- Beacon Street – Continue with cut and caps
- Bay State Road, Beacon Street, and Raleigh Street
- Milling and paving
Annex – 7 am to 6 pm
Load out
- Load out at Bay State Road and Beacon Street to dumpsters with ongoing daily dumpster swaps