Myles Standish Hall – Construction Activity – 11/11/16 – 11/18/16

Myles 11.10.16

For 11/11/16 to 11/18/16:

Deliveries

  •  Subcontractors will receive deliveries all week between 7 a.m. and 6 p.m. on both Beacon Street and Bay State Road.

Onsite Construction

Friday 11/11/16 – No work due Veterans Day

Saturday Work – 11/12/16 – On Saturday, the following work will be occurring onsite from 7 a.m. to 5 p.m. Activities will require workers, trucks, and equipment in the point park. The man and material hoist will be running.

  • Demo of façade on the Bay State Road and Beacon Street sides of the building
  • Installation of relieving angles off of fraco on the Bay State Road side of the building
  • Removal of staging at Annex in the alley
  • Clean and stock staging for masons on the Bay State Road and Beacon Street sides of the building.
  •  Interior framing and interior demolition
  • Loading drywall on the 9th floor from the hoist on the Beacon Street side of the building

Demolition

  • Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster with ongoing daily dumpster swaps.
  • Demolition and load out of basement
  • Exterior demolition on Bay State Road and Beacon Street
  • Demolition of floor 1 (interior)

Masonry Restoration (Exterior – Bay State Road and Beacon Street)

  • Continue rebuilding exterior façade above Annex off of swing staging.
  • Continue rebuilding exterior façade on the Bay State Road side of the building.
  • Continue with installation of windows.

 Roof (Exterior)

  • Continue with installation of roofing.

Alley Between Annex and Myles at Bay State Road (Exterior)

  • Continue with installation of brick and windows.

Site  Utility Work

  • Continue with utilities within the site fence on the Beacon Street side of the building and in the point park.

For questions, please contact Brian Kelley.