Myles Standish Hall – Construction Activity – 7/2/16-7/8/16
For 07-02-16 to 07-08-16:
Deliveries
- Subcontractors will receive deliveries all week from 7 a.m. to 5 p.m. on both Beacon Street and Bay State Road.
Onsite Construction
Saturday 7/2/16 — No work
Monday 7/4/16 — No work (holiday)
Man and Material Hoist Construction
- Constructing loading dock and infill around gates.
Demolition Abatement
- Load out at Beacon Street – Load out demolition debris from 1st floor to dumpster.
- Continue with load out down chute – Interior
- Demolition and load out of basement.
- Abatement on floors 7 and 8 – Interior
- Demolition after abatement at buffer zone on floors 4 and 5.
- Demolition of floor 9.
- Continue with demolition of existing freight elevator – Interior
Masonry Restoration (Exterior)
- Continue with masonry demo on the Bay State Road side of the building.
- Start installation of concrete masonry units (CMU).
- Start masonry demo on the Beacon Street side of the building.
- Start masonry demo on swing above the Annex.
Roof (Exterior)
- Installation of CMU at parapet.
Site Work
- Form and pour new foundation walls for transformer pad.
- Backfill Annex alley after concrete pour.

For questions, please contact Brian Kelley.