NEIDL in the News
Site contractor will work on grading
National Emerging Infectious Diseases Laboratories June 20, 2008 Construction will take place Saturday, June 21, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Electrical contractor and building management team will work on all floors. The Concrete contractor will work on Level 1 and the Millwork contractor will work on... More
New appointment to BioLab committee
South End News June 19, 2008 by Linda Rodriguez managing editor Three South End residents have been appointed or re-appointed to the Community Liaison Committee of the controversial Boston University BioLab, rounding out the six-member committee. Glen Berkowitz, the chair of the CLC in 2007 and a member of the Worcester Square Area Neighborhood Association, was... More
Members Appointed to Community Group for National Emerging Infectious Diseases Laboratories at BU
Boston University Medical Campus For Immediate Release May 10, 2010 Contact: Ellen Berlin 617-638-6838, ellen.berlin@bmc.org Boston, MA—Three members were appointed to fill the open positions on the six-member Community Liaison Committee (CLC) of the National Emerging Infectious Diseases Laboratories (NEIDL). One current member and two new members have been chosen by Karen Antman, MD, Provost... More
Casework installer will work on Level 5
National Emerging Infectious Diseases Laboratories June 12, 2008 Construction will take place Saturday, June 14, 2008 between the hours of 7:00 a.m. and 4:00 p.m. Building automation and electrical work will take place on all levels. The Casework installer will work on Level 5. The Drywall contractor will work on Level 6 while... More
Biolab requires further review, panel tells NIH
Boston Globe Jun 6, 2008 By Christopher Baxter, Globe CorrespondentAn elite panel of scientists recommended today that federal health authorities conduct the most extensive safety review so far of the controversial laboratory being built by Boston University. The most dangerous germs require further study, the blue-ribbon panel told the director of the National... More
Electrical contractor will work on all floors
National Emerging Infectious Diseases Laboratories June 6, 2008 Construction will take place Saturday, June 7, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Concrete contactor will work on Level 1. The Controls contractor will work on Levels 3 and 7. The Special coatings contractor will work on Level 6. More
Concrete contractor will work on Level 1
National Emerging Infectious Diseases Laboratories May 30, 2008 Construction will take place Saturday, May 31, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Controls contactor will work on all levels. The Concrete contractor will work on Level 1. The Electrical contractor will work on Levels 3, 5 and 7. More
Paint contractor will paint Stair #2
National Emerging Infectious Diseases Laboratories May 23, 2008 Construction will take place Saturday, May 24, 2008 between the hours of 7:00 a.m. an 4:30 p.m. The paint contractor will paint Stair #2. The building automation system contractor will work in various locations. Adverse impacts due to excessive vibration or noise are not... More
Boston University School of Medicine’s CityLab Academy Graduation a Success
Boston University School of Medicine For Immediate Release May 21, 2008 Contact: Allison Rubin, 617-638-8491, allison.rubin@bmc.org Boston University School of Medicine’s CityLab Academy Graduation a Success (Boston)—Thirty-nine students graduated from Boston University School of Medicine’s (BUSM) CityLab Academy last Thursday. CityLab Academy is a free nine-month academic and laboratory skills training program for qualified high... More
Panel urges review of possible lab threats
Boston.com May 17, 2008 By Stephen Smith Globe Staff Federal health officials should conduct a rigorous review of potential threats posed by a controversial Boston University laboratory and make sure the surrounding neighborhood is not excluded from the process, a panel of top scientists said yesterday. The chairman of the board, Dr. Adel Mahmoud of... More
Interior electrical work will take place on Levels 4, 5, 6 and 7
National Emerging Infectious Diseases Laboratories May 16, 2008 Construction will take place Saturday, May 17, 2008 between the hours of 7:00 a.m. and 4:00 p.m. Interior electrical work will take place on Levels 4, 5, 6 and 7. Adverse impacts due to excessive vibration or noise are not anticipated.
Electrical and millwork installation will take place on Levels 4 and 5
National Emerging Infectious Diseases Laboratories May 9, 2008 Construction will take place Saturday, May 10, 2008 between the hours of 7:00 a.m. and 4:00 p.m and Sunday, May 11, 2008 between 8:00 a.m. and 4:00 a.m. On Saturday, electrical and millwork installation will take place on Levels 4 and 5. On Sunday, More
NIH panel hears risk assessment suggestions
South End News May 8, 2008 by Linda Rodriguez managing editor The National Institutes of Health (NIH) took suggestions on conducting an in-depth risk assessment of the Boston University BioLab from the committee that roundly rejected the agency’s previous risk assessment in November. The NIH’s blue ribbon panel heard the recommendations of the National Research... More
NIH Announcement on Blue Ribbon Panel
National Institutes of Health May 7, 2008 The National Institutes of Health is convening a public meeting of the NIH Blue Ribbon Panel, a Working Group of the Advisory Committee to the Director, to advise on Risk Assessment of the National Emerging Infectious Diseases Laboratories. May 16, 9AM – 12 PM Massachusetts State House Gardner... More
Scientists call for expanded safety review of BU biolab
Boston Globe May 3, 2008 By Stephen Smith, Globe Staff An elite panel of scientists this morning urged the federal government to substantially expand its safety review of a controversial research laboratory being built by Boston University. The recommendation comes from the National Research Council, an independent advisory board of scientists, which sharply criticized... More
Drywall, carpentry and flooring work will take place on Level 2
National Emerging Infectious Diseases Laboratories May 1, 2008 Construction will take place Saturday, May 3, 2008 between the hours of 7:00 a.m. and 4:30 p.m. Drywall, carpentry and flooring work will take place on Level 2. Casework will take place on Levels 4 and 6. Work on controls and electrical systems will... More
Coating contractor will work on Level 6
National Emerging Infectious Diseases Laboratories April 18, 2008 Construction will take place Saturday, April 19, 2008. The Coating contractor will work on Level 6. Adverse impacts due to excessive vibration or noise are not anticipated.
Coating contractor will work on Levels 2 and 6
National Emerging Infectious Diseases Laboratories April 11, 2008 Construction will take place Saturday, April 12, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Coating contractor will work on Levels 2 and 6. Adverse impacts due to excessive vibration or noise are not anticipated.
Coating contractor will be work on Levels 2 and 6
National Emerging Infectious Diseases Laboratories April 4, 2008 Construction will take place Saturday, April 5, 2008 between 7:00 a.m. and 4:00 p.m. The Coating contractor will work on Levels 2 and 6. Adverse impacts due to excessive vibration or noise are not anticipated.
The Painting contractor will work on all levels
National Emerging Infectious Diseases Laboratories March 21, 2008 Construction will take place Saturday, March 22, 2008 between the hours of 7:00 a.m. and 4:30 p.m. The Painting contractor will work on all levels. Adverse impacts due to excessive vibration or noise are not anticipated.