The Mechanical trades will work inside the building
National Emerging Infectious Diseases Laboratories Janaury 4, 2008 Construction will…
The precast erector will sandblast the east facade exterior panels
National Emerging Infectious Diseases Laboratories December 14, 2007 Construction will…
Finish coatings contractor will work on Level 2
National Emerging Infectious Diseases Laboratories December 7, 2007 Construction will…
Boston University Medical Center Statement on the National Research Council Report
Boston University Medical Center November 29, 2007 We recognize that…
Construction will take place Saturday and Sunday, November 17 and 18, 2007
National Emerging Infectious Diseases Laboratories November 16, 2007 Construction will…
The hoist installer will remove the temporary hoist
National Emerging Infectious Diseases Laboratories November 8, 2007 Construction will…
EXTENSION OF COMMENT PERIOD FOR NIH REPORT
The National Institutes of Health October 30, 2007 The National…
The site work contactor will work on the perimeter fence and walls
National Emerging Infectious Diseases Laboratories October 25, 2007 Construction will…
The elevator contractor will work on Service Car #4
National Emerging Infectious Diseases Laboratories October 20, 2007 Construction will…
NSTAR will work on site along Albany Street
National Emerging Infectious Diseases Laboratories October 12, 2007 Construction will…