The HVAC contractor will continue work on Levels 1, 7, and 8

National Emerging Infectious Diseases Laboratories

August 8, 2007

Construction will take place Saturday, August 11, 2007 between the hours of 7:00 a.m. and 4:00 p.m. The HVAC contractor will continue work on  Levels 1, 7 and 8. The Plumbing contractor will work on Levels 1 and 2 and the project fence company will work on fencing on Albany Street. Adverse impacts due to excessive vibration or noise are not anticipated.