Casework installer will work on Level 5

National Emerging Infectious Diseases Laboratories

June 12, 2008

Construction will take place Saturday, June 14, 2008 between the hours of 7:00 a.m. and 4:00 p.m. Building automation and electrical work will take place on all levels. The Casework installer will work on Level 5. The Drywall contractor will work on Level 6 while the Coatings contractor works on both Levels 2 and 6. Adverse impacts due to excessive vibration or noise are not anticipated.