Electrical and millwork installation will take place on Levels 4 and 5

National Emerging Infectious Diseases Laboratories

May 9, 2008

Construction will take place Saturday, May 10, 2008 between the hours of 7:00 a.m. and 4:00 p.m and Sunday, May 11, 2008 between 8:00 a.m. and 4:00 a.m. On Saturday, electrical and millwork installation will take place on Levels 4 and 5. On Sunday, the mechanical contractor will work on all floors.  Adverse impacts due to excessive vibration or noise are not anticipated.