The site work contactor will work on the perimeter fence and walls

National Emerging Infectious Diseases Laboratories

October 25, 2007

Construction will take place Saturday, October 27 between the hours of 7:00 a.m. and 4:00 p.m and Sunday, October 28, 2007 between the hours of 8:00 a.m. and 4:30 p.m.  NSTAR will work on Level 1. Iron workers will work on Level 7.  The plumbing contractor will work on Levels 1 and 7 while the HVAC contractor works on Levels 1, 7 and 8. The glass, fire proofing and metal panel contractors will work on the exterior. The site work contactor will work on the perimeter fence and walls. On Sunday, the Pre-cast contractor will work on the exterior panels. Adverse impacts due to excessive vibration or noise are not anticipated.