Coatings contractor will prep concrete surfaces on Level 2
National Emerging Infectious Diseases Laboratories
September 13, 2007
Construction will take place Saturday and Sunday, September 15 and 16, 2007 between the hours of 7:00 a.m. and 4:00 p.m. On Saturday, Otis Elevator will work on the freight elevators and the coatings contractor will prep concrete surfaces on Level 2. The HVAC contractor will work on Level 7. On Sunday, the electrical contractor will work on Level 7 and on site electrical. Adverse impacts due to excessive vibration or noise are not anticipated.