Special Coatings contractor will work on a mockup

National Emerging Infectious Diseases Laboratories

June 15, 2007

Construction will take place  Saturday, June 16, 2007 between the hours of 7:00 a.m. and 4:00 p.m.  The Special Coatings contractor will work on a mockup. The  precast and steel erectors will work on detailing the precast and on elevator  tubes and roof frames, respectively. Interior waterproofing of the precast  will take place and the HVAC Contractor will work on Level 7. Adverse impacts  due to excessive vibration or noise are not  anticipated.