Installation of Pre-Cast and Steel Erector

National Emerging Infectious Diseases Laboratories

June 1, 2007

Construction will take place Saturday, June 2, 2007 between the hours of 7:00 a.m. and 4:00 p.m. The pre-cast concrete panel erector will be on site to continue the installation of pre-cast and the steel erector will be on site to install miscellaneous supports. In addition, the HVAC mechanical contractor will be on site working on Level 7. Adverse impacts due to excessive vibration or noise are not anticipated.