Construction will take place  Saturday, June 23 and Sunday, June 24, 2007 between the hours of 7 a.m. and  4:00 p.m. On Saturday, June 23, the pre-cast fabricator and pre-cast  erector will respectively work on exterior pre-cast cleaning and pre-cast  panel alignment. Installation of mechanical piping and waterproofing  will take place on Level 7. On Sunday, June 24, work will resume on exterior  pre-cast cleaning and alignment of pre-cast panels. Adverse impacts due to  excessive vibration or noise are not  anticipated.