Erection of Steel and Installation Decking
National Emerging Infectious Diseases Laboratories
January 12, 2007
Construction will take place Saturday, January 13, 2007 between the hours of 7:00 am and 3:30 p.m. Erection of steel and installation of floor decking and welding connections will continue. Concrete work will take place on the second and fifth floors while electrical and plumbing contractors will work on the first, second and fourth floors. Work will also be done on stair installations. Adverse impacts due to excessive vibration or sound are not anticipated.