Bolting, Decking on All Levels
National Emerging Infectious Diseases Laboratories
December 15, 2006
Construction will take place Saturday, December 16, 2006 between 7:00 a.m. and 4:00 p.m. Iron workers will work on steel erection of the 6th and 7th floors, including bolting and decking on all levels and installation of safety railings. In addition, the site contractor will be on site for the backfill of the steam behind the Evans building and the concrete contractor will be preparing for concrete placement on the 2nd floor and remaining pieces of the perimeter foundation. Keyspan will be on site working on the gas line for temporary heat. Adverse impacts due to excessive vibration or noise are not anticipated.