Warren Towers Renovation – Construction Update – 2/21/2025
General Project Information Work on the exterior, outside student rooms, will be performed from 9:00 am until 5:00 pm. Deliveries, work on the street level, and work inside the fenced construction area will begin at 7:00 am. The team is currently in the main renovation phase of the project. Emergency... More
Warren Towers Renovation – Construction Update – 2/14/2025
General Project Information Work on the exterior, outside student rooms, will be performed from 9:00 am until 5:00 pm. Deliveries, work on the street level, and work inside the fenced construction area will begin at 7:00 am. The team is currently in the main renovation phase of the project. Emergency... More
Warren Towers Renovation – Construction Update – 2/7/2025
General Project Information Work on the exterior, outside student rooms, will be performed from 9:00 am until 5:00 pm. Deliveries, work on the street level, and work inside the fenced construction area will begin at 7:00 am. The team is currently in the main renovation phase of the project. Emergency... More
Warren Towers Renovation – Construction Update – 1/31/2025
General Project Information Work on the exterior, outside student rooms, will be performed from 9:00 am until 5:00 pm. Deliveries, work on the street level, and work inside the fenced construction area will begin at 7:00 am. The team is currently in the main renovation phase of the project. Emergency... More
Warren Towers Renovation – Construction Update – 1/24/2025
General Project Information Work on the exterior, outside student rooms, will be performed from 9:00 am until 5:00 pm. Work on the street level will be performed from 7:00 am until 5:00 pm. The team is currently in the main renovation phase of the project. Emergency Contacts: Owners Representative –... More
Warren Towers Renovation – Construction Update – 1/17/2025
General Project Information Work on the exterior, outside student rooms, will be performed from 9:00 am until 5:00 pm. Work on the street level will be performed from 7:00 am until 5:00 pm. The team is currently in the main renovation phase of the project. Emergency Contacts: Owners Representative –... More
Warren Towers Renovation – Construction Update – 1/10/2025
General Project Information Daily works are from 7:00 am until 3:30 pm. Nightly works are from 8:00 pm until 7:00 am. The team is currently in two phases, the Main renovation project and the Winter Intersession investigation/ enabling phases. Emergency Contacts Owners Representative – Leftfield Project Management: Corey Davidson... More
Warren Towers Renovation – Construction Update – 1/2/2025
General Project Information Daily works are from 7:00 am until 3:30 pm. Nightly works are from 8:00 pm until 7:00 am. The team is currently in two phases, the Main renovation project and the Winter Intersession investigation/ enabling phases. South Alley Access is limited, please use the rear alley... More
Warren Towers Renovation – Construction Update – 12/20/2024
General Project Information Current Phase Winter Intersession investigation/enabling Next week is the main renovation project kickoff and start Work hours: Day Shift 7:00 AM – 3:30 PM Night Shift 8:00 PM – 8:00 AM South Alley Access: Please use the rear alley behind the building for access to 111 Cummington... More
Warren Towers Renovation – Construction Update – 12/13/2024
General Project Information Daily works are from 7:00 am until 3:30 pm. The team is currently in the enabling phase, crews on site are small, mainly working in the parking garage, rear alleyway, and in Cummington Mall. Emergency Contacts Owners Representative – Leftfield Project Management: Corey Davidson - 508-330-8489 Contractor... More