Major Chiller Replacement for the Metcalf Science Center

By Leslie MonteiroAugust 3rd, 2020in Featured Content

Chris Gorman from FMO's Engineering & Building Systems team lead the efforts to finish replacing two chillers at 712 beacon street last week. These chillers were deferred maintenance replacement of equipment that has exceed their useful life. The HVAC contractor removed two existing air cooled chillers and installed two 200 ton air cooled screw chillers... More

PDC Leads COVID-19 Signage Efforts

By Leslie MonteiroAugust 3rd, 2020in Featured Content

Jeff Hoseth, Max Noe, and David Flynn of Planning, Design & Construction (PDC) are coordinating the procurement and installation of COVID-19 signage across BU's three campuses. To date, north of 65,000 signs are needed, of which over 50,000 have been ordered. The team is working to get all signage for all phases of re-opening... More